Delivery schedule achievement
QCD: measuring manufacturing performance, Published by the Department of Trade and Industry in 2004 suggested that Delivery Schedule Achievement (DSA): ‘…measures how well a supplier matches the planned delivery requirement of the customer…. DSA is a function of good plant performance, which in turn is an indication of good management. Good plant performance is demonstrated when production flows through the plant without interruptions.’
DSA measures actual delivery performance against the planned delivery schedule.
- Late and early deliveries are called ‘not on time’
- Deliveries of too many or too few parts and parts that don’t conform to the job are ‘Incorrect quantity deliveries’
Delivery Schedule Achievement (%) = 100 x (planned deliveries - (not on time + incorrect quantities))/planned deliveries.
Deliveries that area not on time and incorrect quantity should only be counted once.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
ECA welcomes plans to strengthen subcontractor quality control.
Combining mid-career qualifications with experience broadens career opportunities.
Why being a mentor can help your career.
Channel 4 broadcaster to host 125th anniversary ceremony.
Listed structures on the rail network
Heritage interests and operational requirements must be balanced.
Historic England publishes research into embodied carbon when retrofitting traditional buildings.
New Prime Minister delivers on ECA call for cut in electricity costs.
CIOB reacts to the announcement of Andy Burnham as Prime Minister.
Heritage and conservation science workforce survey - Have your say.
England's Suburbs 1820-2020. Book review.
New, more proportionate and targeted approach for higher-risk building assessments.
Government brings British Steel into public ownership.