Delivery schedule achievement
QCD: measuring manufacturing performance, Published by the Department of Trade and Industry in 2004 suggested that Delivery Schedule Achievement (DSA): ‘…measures how well a supplier matches the planned delivery requirement of the customer…. DSA is a function of good plant performance, which in turn is an indication of good management. Good plant performance is demonstrated when production flows through the plant without interruptions.’
DSA measures actual delivery performance against the planned delivery schedule.
- Late and early deliveries are called ‘not on time’
- Deliveries of too many or too few parts and parts that don’t conform to the job are ‘Incorrect quantity deliveries’
Delivery Schedule Achievement (%) = 100 x (planned deliveries - (not on time + incorrect quantities))/planned deliveries.
Deliveries that area not on time and incorrect quantity should only be counted once.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Your views needed - a strategy for the professions, trades and occupations.
Confronting competency, codes, capacity and costs.
The hidden risk in modern construction supply chains.
Construction Management, 10 June
24 months to 14: CITB launches accelerated apprenticeships.
Bridging the gap between clients and contractors
Concerns remain around contractor quality, capability, and delivery.
Construction Management, 10 June.
Heat pumps beat boilers in new home tests.
Building Safety Act implementation in Wales
CIAT to host industry panel on 26 June.
New and updated CLC building safety guidance.
New UK National Buildings Database.
Building Safety Wiki Interviews
Chief executive of the British Woodworking Federation.
Planning condition discharge in England and Wales
A brief explanation from a building compliance expert, with further links.